Lots 1-4: Unit construction completed, for punchlist compliance
Lots 5-8: Unit construction completed,but awaiting for homeowner punchlist Lot 6: Unit turned over to new home owner Lot 9: Unit construction is ongoing. Completion is currently at 43% |
Lots 6-10: Unit construction completed, for punchlist compliance
Lots 2: Lot for layout and excavation Lot 9: Unit construction is ongoing. Completion is currently at 43% Lot 6: Unit turned over to new home owner |
Lots 2-10: Unit construction is ongoing. Completion is currently at 70% |